Work order steps are the instructions to complete work orders. A work order can be completed without completing all the steps. 

1. Org Configuration

Organization may choose to require all steps be completed before work orders can be completed. The following screenshot shows that both corrective and PM work orders require steps to be completed. This is done by enabling step requirement at EAM company level.


2. Site Configuration

For multi-site implementation, Calem allows each site to configure own step requirements.


3. Step Requirement by Status

This option allows one to configure step requirements for each work order status. For instance, for work orders to enter "InProcess" status, step 10 and 20 must be completed. See this blog for more information.